County commissions design for a bigger south highway garage after years of cramped, outdoor repairs
Who it touches: Residents in the southern part of the county who depend on county crews for snowplowing and road maintenance could see faster equipment turnaround once the new bays are built.
Commissioners approved a $45,000 engineering contract with Walbeeser Engineering to design an addition to the county highway department's south garage, after the county engineer said moving operations to a different property wasn't cost-effective. 0:15:30 — open the recording, cued to 15 minutes 30 seconds
The addition would be a 60-by-80-foot building adding three vehicle bays plus a wash bay; a commissioner said the south garage currently has only two bays that vehicles pull into but can't pull through, so crews have had to repair broken-down trucks and equipment outdoors, including in winter weather. (16:09, 0:17:05 — open the recording, cued to 17 minutes 5 seconds
The contract also includes a roughly $16,000 site-design subcontract to address drainage on the property, and the county engineer said the added bays would let crews pre-load materials for a faster response to winter storms. (16:10, 0:18:41 — open the recording, cued to 18 minutes 41 seconds
More from the record
- Addition size and bay shortage0:16:09 (16 minutes 9 seconds)
- Drainage subcontract and winter-response benefit, 16:10 / 18:410:16:10 (16 minutes 10 seconds)
- No construction budget yet0:16:34 (16 minutes 34 seconds)
- MVH/road funds can't be used without cuts0:19:00 (19 minutes)
- Would likely need a bond0:19:40 (19 minutes 40 seconds)
- Voice vote approval0:21:55 (21 minutes 55 seconds)
Outcome
Approved on a voice vote; construction funding not yet identified
Approved on a voice vote; no per-member tally was recorded. The $45,000 pays only for design work — the county engineer said no construction funding has been budgeted yet, and it will likely need a bond or another outside funding source, since state road-maintenance funds can't be used here without cutting other road work. (16:34, 19:00, 19:40, 21:55)