Board sets aside the YMCA expansion's last $83,000 as an owner contingency fund

Verification status

Flagged — not yet verified. We have not been able to confirm part of this item against the record. We publish the flag rather than sit on the item; check the source yourself below.

How we attribute this: speaker_122 → Mark Merrill — the chair names him immediately before he speaks: "...the why renovation talk in so mark merrill yep uh thank you so uh this will" [t=449], and this label continues the same sentence and presentation without interruption: "be gmp number three um currently there is no owner contingency allowance in the budget..." [t=457]. One naming event by direct address (not self-stated), so held at `probable` per the meeting's speaker roster.

Who it touches

Tracked in the archive

The Terre Haute Board of Public Works and Safety approved a third amendment (GMP 3) to the construction contract for the YMCA expansion, creating an owner-contingency fund — money set aside for problems outside the contractor's control, like unexpected asbestos — that the project's budget didn't have until now. 0:07:29 — open the recording, cued to 7 minutes 29 seconds

Mark Merrill, presenting the project, told the board GMP2 (the contractor's prior guaranteed maximum price — a construction contract that caps what the contractor can charge) was $11,517,000 against a total project budget of $11,600,000, leaving about $83,000 with no line item; this amendment assigns that remainder to the new contingency fund. 0:07:37 — open the recording, cued to 7 minutes 37 seconds

He said the project has already drawn on a separate construction-contingency fund for smaller asbestos-abatement work, which is the owner's responsibility rather than the contractor's. 0:08:10 — open the recording, cued to 8 minutes 10 seconds

More from the record

Outcome

Approved on a voice vote; no per-member tally was recorded.

Approved on a voice vote; no per-member tally was recorded.

GMP 3 introduced — cued to 0:07:29 (7 minutes 29 seconds)

This summary was drafted with AI assistance and reviewed by an editor against the recording and documents linked above. Nothing publishes without a resolvable source.