Ray Park clubhouse work gets $25,232 and 30 more days to remove lead paint

Who it touches

Tracked in the archive

The Board of Public Works approved change order number eight (a formal amendment to the construction contract) for the Ray Park clubhouse project, adding $25,232 and 30 more days so the contractor can remove lead paint found on the building. (12:46, 0:13:09 — open the recording, cued to 13 minutes 9 seconds

Everyone had first believed the building had no lead paint; the designer's test came back negative, but the painters' own testing found it, so it has to be remediated. (12:59, 0:13:59 — open the recording, cued to 13 minutes 59 seconds

The contractor first asked for 60 more days; after the board pushed back it asked for 30. 0:13:09 — open the recording, cued to 13 minutes 9 seconds

City staff said the change is to the contract between the city and the construction company. 0:13:37 — open the recording, cued to 13 minutes 37 seconds

This follows change order seven on Sept.

14, which moved the clubhouse's completion from September to November.

([Sept.

14, 22:42](https://www.youtube.com/watch?v=cnxC5OyTZ-c&t=1362))

More from the record

Outcome

Approved on a voice vote

Approved on a voice vote; no per-member tally was recorded. (14:25)

Change order eight introduced — cued to 0:12:46 (12 minutes 46 seconds)

This summary was drafted with AI assistance and reviewed by an editor against the recording and documents linked above. Nothing publishes without a resolvable source.