Flagged · UnverifiedTerre Haute Board of Public Works · Oct 26, 2026 · This meeting

Turn to the River Phase 3 bid opens at $1.35 million; board waits on engineering review

Verification status

Flagged — not yet verified. We have not been able to confirm part of this item against the record. We publish the flag rather than sit on the item; check the source yourself below.

Who it touches:

Tracked in the archive

The Board of Public Works opened a bid for Phase 3 of the Turn to the River project with a base amount of $1,352,138.25. (14:46, 0:15:10 — open the recording, cued to 15 minutes 10 seconds

The bid includes an alternate (an optional add-on priced separately) of $18,750 for irrigation, which staff said was overlooked in the design and added so it would be included. (15:10, 0:15:47 — open the recording, cued to 15 minutes 47 seconds

The board took the bid under advisement (held it without accepting it) so the engineering department can review it. 0:16:10 — open the recording, cued to 16 minutes 10 seconds

One speaker said it should come back with a favorable recommendation, and another said the bid came in a little under an earlier figure. (16:16, 0:16:34 — open the recording, cued to 16 minutes 34 seconds

More from the record

Outcome

Bid taken under advisement; no award

Taken under advisement on a voice vote; no contract was awarded and no per-member tally was recorded. (16:46)

Bid opening begins — cued to 0:14:46 (14 minutes 46 seconds)

This summary was drafted with AI assistance and reviewed by an editor against the recording and documents linked above. Nothing publishes without a resolvable source.